Schedule

September, 2001
Finish Schematic Design
September, 2001 - April, 2002
Design Development
March - August, 2002
Construction Documents
Summer, 2002
Preliminary Site Work
June, 2002 - August, 2004
Phase I Construction
August, 2004 - August, 2005
Phase II Construction